Seattle vs. Bellevue: ADU rules side by side.
Same state floor, different size limits, parking rules and permit paths.

Seattle and Bellevue sit across Lake Washington and under the same state ADU law, so the big rules now match: two ADUs per lot, no owner-occupancy requirement, and the right to sell an ADU as a condominium. The differences are in the details, and they are the details that decide what fits on a particular lot.
The state floor both cities must meet
Washington’s 2023 ADU law (RCW 36.70A.681) requires cities inside urban growth areas to allow, on any lot where a house is allowed: two ADUs in any combination of attached and detached; a maximum size of at least 1,000 sq ft; a height limit of at least 24 feet; no owner-occupancy requirement; no off-street parking within half a mile walking distance of a major transit stop; and impact fees of no more than 50% of a new house’s. Both cities had to bring their codes in line by mid-2025.
Side by side
| Rule | Seattle | Bellevue |
|---|---|---|
| ADUs per lot | 2, attached or detached | Up to 2, attached or detached |
| Detached ADUs | Allowed for years; long-established backyard-cottage program | New: before the 2025 update only attached ADUs were allowed |
| Maximum size | 1,000 sq ft per ADU (see our Seattle page) | 1,200 sq ft, with exceptions the Director can approve (e.g. conversions of existing detached structures); up to 250 sq ft of parking or unheated storage excluded |
| Off-street parking | Not required | None under 1,000 sq ft or within ½ mile of a major transit stop; 1 space for 1,000–2,000 sq ft |
| Owner occupancy | Not required | Not required (removed in 2023) |
| Sale as a condo | Allowed | Allowed (prohibition removed in 2023) |
| Pre-approved plans | Yes, ADUniverse library; most permits in 2–6 weeks per the city | Ask the city |
| Permits | SDCI; side sewer by Seattle Public Utilities since Oct 1, 2025 | Bellevue Development Services |
| Code section | SMC 23.42.022 | LUC 20.20.120 |
| Cost factor in our model | × 1.08 | × 1.10 |
Bellevue figures follow the city’s 2025 middle-housing and ADU amendment as presented to its Planning Commission, adopted to meet the state’s June 30, 2025 deadline. Codes change; the linked code section governs.
What the differences mean on a real lot
Size
Bellevue’s 1,200 sq ft cap, plus the garage and storage exclusion, leaves more room for a two-bedroom unit or an ADU above a garage. In Seattle, 1,000 sq ft is enough for a comfortable two-bedroom, but the layout has to be efficient.
Parking
Neither city requires parking for a typical ADU. In Bellevue it comes into play only for larger units away from frequent transit; in Seattle it does not apply.
Experience and process
Seattle has permitted backyard cottages for years and has a pre-approved plan library; that institutional experience shows in a predictable process. Bellevue’s detached-ADU rules are new, so expect reviewers and applicants to be working out details on early projects. A complete first submittal matters even more there.
Cost
Our model puts Bellevue labor and permitting about 2% above Seattle’s. On an 800 sq ft detached ADU that is a few thousand dollars, much less than the difference a long side sewer or a sloped lot makes.
Before you design in either city
- Confirm the current code section: SMC 23.42.022 in Seattle, LUC 20.20.120 in Bellevue.
- Check for critical areas (slopes, wetlands, streams); the state ADU rules do not apply on those lots.
- Locate the sewer main and the existing side sewer before choosing where the ADU goes.
Rules for 18 cities and three counties, in the same format: ADU rules by city. The Seattle details are on our Seattle page.
SOURCES
- RCW 36.70A.681 — Accessory dwelling unitsREVISED CODE OF WASHINGTON
- Seattle Municipal Code 23.42.022 — Accessory dwelling unitsCITY OF SEATTLE · MUNICODE
- Accessory Dwelling UnitsSEATTLE DEPT. OF CONSTRUCTION AND INSPECTIONS
- Middle housing LUCA staff report and draft code (April 2025)CITY OF BELLEVUE · DEVELOPMENT SERVICES
- ADU reform (Ordinance 6746, 2023)CITY OF BELLEVUE
A plain-language summary, not legal, tax or lending advice. Rules change: the linked source governs. How we keep pages current →